MUMBAI: (May 20) With the launch of a 40 metre-long girder near Surat in Gujarat, 300 km of viaducts for the Mumbai-Ahmedabad bullet train project has been completed, the National High Speed Rail Corporation (NHSRCL) said on Tuesday.
According to the NHSRCL, of the 300 km of the superstructure, 257.4 km is constructed through the Full Span Launching Method (FSLM), including 14 river bridges, 37.8 km through Span by Span (SBS), 0.9 km of steel bridges (10 spans ranging from 60 to 130 m in 7 bridges), 1.2 km PSC bridges (20 spans ranging from 40 to 80 metres in 5 bridges) and 2.7 km in station building.
Besides the viaducts, 383 km of pier work, 401 km of foundation and 326 km of girder casting has been completed for the 508-km bullet train project, the agency said.